The council approved a $3,656,716.25 contract for Birdland Park Phase 1A, including raising the flood-prone Neal Smith Trail and a new boat ramp, by a 7–0 vote.

Des Moines City Council · Mar 9, 2026 · Roll call 26-0331

Approved plans and specifications and named Iowa Earth Works, LLC (Huxley) the lowest responsive, responsible bidder at $3,656,716.25. Moved by Westergaard, seconded by Gatto. Passed 7–0; no members voted no.

How each member voted

OfficialSeatVote
Connie BoesenMayorYes
Carl VossAt-largeYes
Mike SimonsonAt-largeYes
Rob X. BarronWard 1Yes
Linda WestergaardWard 2Yes
Josh MandelbaumWard 3Yes
Joe GattoWard 4Yes

Unanimous votes are shown as-is and are not used to compare officials.

More from the record

Phase 1A is the first of three parts of Phase 1 of the Birdland Park and Marina Master Plan, adopted after public meetings that drew over 200 people and 350+ survey responses. It raises and realigns about 0.4 miles of the Neal Smith Trail so it closes less often for flooding (over 160,000 trail uses were counted nearby in 2024), adds a trail spur to the 2nd Avenue Bridge and Central Place Trail, two shelters, three fishing spots (two ADA-accessible), a power boat ramp with parking, an ADA pier and dock, over 100 trees and shrubs, about 3.5 acres of prairie and savanna, and about 1,800 feet of shoreline work. The full master plan was estimated at $54.4 million in 2021. Three bids were received. Council Communication 26-077 (saved copy)

The alternative

No other options were presented in the record.

Parks and outdoors

Who
Trail users, anglers, boaters and visitors to Birdland Park
How
Higher trail, new boat ramp, shelters, fishing areas, native plantings and shoreline work
When
Spring 2026 to late spring 2027
Source
Council Communication 26-077 (saved copy)

Money

Who
City and grant funders
How
$3,656,716.25 (estimate $3,700,000): $1,758,000 in state and federal grants, $822,721.25 local option sales tax and $1,075,995 general obligation bonds
When
2025-26 Capital Improvement Program
Source
Council Communication 26-077 (saved copy)

From the official minutes summary: all seven members were present (roll call 26-0279) and only Nays are named, so the rest voted yes.

Source Agenda for the whole meeting, item 42 (saved copy) · Full minutes for the whole Mar 9, 2026 meeting, p. 8 (roll call 26-0331) (saved copy) · Council Communication 26-077 (saved copy)

What you can do

Have your say

Public comment: use the city’s Request to Speak form before 5 PM CT the day before a meeting.
Written comment: City Clerk, cityclerk@dmgov.org, (515) 283-4209. Mention roll call 26-0331.

Meetings page (saved copy) ·

Contact your officials

Write a letter

Contacts: City Council page (saved copy)

Get email alerts

A short email when the places you follow post new decisions, with links to the official record.

Sign up
6 · Sources

Corrections appear here as dated notes. Nothing is rewritten.