Approval of Pay Application #01 for the Parallel Taxiway Reconstruction
Recorded in the minutes as “Approval of Pay Application #01 for the Parallel Taxiway Reconstruction”. Carried unanimously; names not recorded. Amount in the record: $215,842.36.
What this means (Pay application): A contractor’s request to be paid for work finished so far on an approved project.
More from the record
Recorded in the minutes as: “1. Approval of Pay Application #01 for the Parallel Taxiway Reconstruction. Motion: Moved by Andorf, seconded by Klein approving Pay Application #01 in the amount of $215,842.36 to Concrete Technologies, Inc. Pay Application #01 covers initial payments for mobilization, traffic control, construction survey, contractor’s quality control program and SWPPP preparation and management as well as pavement removal, topsoil stripping and excavation. All documents were reviewed and signed by the engineer and was recommended for approval”.
Motion as recorded: “Moved by Andorf, seconded by Klein approving Pay Application #01 in the amount of $215,842.36 to Concrete Technologies, Inc. Pay Application #01 covers initial payments for mobilization, traffic control, construction survey, contractor’s quality control program and SWPPP preparation and management as well as pavement removal, topsoil stripping and excavation. All documents were reviewed and signed by the engineer and was recommended for approval”.
Source Full minutes for the whole May 4, 2026 meeting (saved copy) · All votes at this meeting