Approval of Pay Application #02 for the Parallel Taxiway Reconstruction
Recorded in the minutes as “Approval of Pay Application #02 for the Parallel Taxiway Reconstruction”. Carried unanimously; names not recorded. Amount in the record: $231,084.18.
What this means (Pay application): A contractor’s request to be paid for work finished so far on an approved project.
More from the record
Recorded in the minutes as: “1. Approval of Pay Application #02 for the Parallel Taxiway Reconstruction. Motion: Moved by Mahler, seconded by Klein approving Pay Application #02 in the amount of $231,084.18 to Concrete Technologies, Inc. Pay Application #02 was for cement treated subgrade, excavation, topsoil handling, subdrain, electrical demo and install, and stored materials for pre-formed concrete joint sealant. All documents were reviewed and signed by the engineer and were recommended for approval”.
Motion as recorded: “Moved by Mahler, seconded by Klein approving Pay Application #02 in the amount of $231,084.18 to Concrete Technologies, Inc. Pay Application #02 was for cement treated subgrade, excavation, topsoil handling, subdrain, electrical demo and install, and stored materials for pre-formed concrete joint sealant. All documents were reviewed and signed by the engineer and were recommended for approval”.
Source Full minutes for the whole Jun 15, 2026 meeting (saved copy) · All votes at this meeting