Approval of Pay Application #24 for the Runway 14/32 Relocation Phase 2
Recorded in the minutes as “Approval of Pay Application #24 for the Runway 14/32 Relocation Phase 2”. Carried unanimously; names not recorded. Amount in the record: $438,589.64.
What this means (Pay application): A contractor’s request to be paid for work finished so far on an approved project.
More from the record
Recorded in the minutes as: “1. Approval of Pay Application #24 for the Runway 14/32 Relocation Phase 2. Motion: Moved by Shelly, seconded by Mahler approving Pay Application #24 in the amount of $438,589.64 to Manatt’s Inc. Pay Application #24 covers the additional topsoil strip, salvage and respread associated with Change Order #3. Pay Application #24 was reviewed and signed by the project manager, which recommended approval”.
Motion as recorded: “Moved by Shelly, seconded by Mahler approving Pay Application #24 in the amount of $438,589.64 to Manatt’s Inc. Pay Application #24 covers the additional topsoil strip, salvage and respread associated with Change Order #3. Pay Application #24 was reviewed and signed by the project manager, which recommended approval”.
Source Full minutes for the whole Jun 15, 2026 meeting (saved copy) · All votes at this meeting