Approval of Pay Application #10 for the Downtown Improvements Phase I Project
Recorded in the minutes as “Approval of Pay Application #10 for the Downtown Improvements Phase I Project”. Carried unanimously; names not recorded. Amount in the record: $103,799.43.
What this means (Pay application): A contractor’s request to be paid for work finished so far on an approved project.
More from the record
Recorded in the minutes as: “1. Approval of Pay Application #10 for the Downtown Improvements Phase I Project. Motion: Moved by Andorf, seconded by Wolling approving Pay Application #10 in the amount of $103,799.43 to TK Concrete, Inc. Pay Application #10 was for completed paving, landscaping and electrical work along Warford Street between 1st Street and the intersection of 2nd Street. All documents were reviewed and signed by the engineer and were recommended for approval”.
Motion as recorded: “Moved by Andorf, seconded by Wolling approving Pay Application #10 in the amount of $103,799.43 to TK Concrete, Inc. Pay Application #10 was for completed paving, landscaping and electrical work along Warford Street between 1st Street and the intersection of 2nd Street. All documents were reviewed and signed by the engineer and were recommended for approval”.
Source Full minutes for the whole Oct 5, 2026 meeting (saved copy) · All votes at this meeting