Waukee Public Safety Building Renovation Project, Bid Packages #02-13: resolution awarding…
Recorded in the minutes as “Waukee Public Safety Building Renovation Project, Bid Packages #02-13 – B. Resolution: Consideration of approval of a resolution awarding contract – Motion: to approve the…”. Passed 5–0; Yes: Anderson, Crone, Grove, Lyon, Pierce.
What this means (Bids and contracts): For public construction, the city approves plans and a cost estimate, takes bids, then awards the contract, usually to the lowest responsible bidder.
How each member voted
| Official | Vote |
|---|---|
| Kala Anderson | Yes |
| Chris Crone | Yes |
| Rob Grove | Yes |
| Lori Lyon | Yes |
| Anna Bergman Pierce | Yes |
More from the record
Recorded in the minutes as: “Waukee Public Safety Building Renovation Project, Bid Packages #02-13 – B. Resolution: Consideration of approval of a resolution awarding contract – Motion: to approve the resolution; seconded by Council Member Crone. City Administrator Deets reviewed the bid tabulation for the individual bid packages, noting that Bid Package #1 was approved by council at an earlier date. He stated that no bids were received for Bid Package #13 so that particular bid package would be rebid. Council Member Crone noted a significant difference between the engineer’s estimate and low bid for Bid Package #9 (Fire Protection); Mr. Deets replied that the project engineer was comfortable with that contractor. He added that the overall project would be funded by local option sales tax and a credit on the geothermal system installed at the new Waukee Public Safety Building. Results of vote:”.
Motion as recorded: “to approve the resolution; seconded by Council Member Crone. City Administrator Deets reviewed the bid tabulation for the individual bid packages, noting that Bid Package #1 was approved by council at an earlier date. He stated that no bids were received for Bid Package #13 so that particular bid package would be rebid. Council Member Crone noted a significant difference between the engineer’s estimate and low bid for Bid Package #9 (Fire Protection); Mr. Deets replied that the project engineer was comfortable with that contractor. He added that the overall project would be funded by local option sales tax and a credit on the geothermal system installed at the new Waukee Public Safety Building. Results of vote:”.
Source Full minutes for the whole Apr 6, 2026 meeting, p. 2 (saved copy) · All votes at this meeting