Resolution awarding contract [2026 Downtown Street Improvements Project], deferred during the…

Waukee City Council · Apr 20, 2026 · Getting around

Recorded in the minutes as “Resolution: Consideration of approval of a resolution awarding contract [2026 Downtown Street Improvements Project], deferred during the April 6, 2026, regular city council…”. Passed 4–0; Yes: Crone, Grove, Lyon, Pierce. Amount in the record: $1,466,984.39.

What this means (Bids and contracts): For public construction, the city approves plans and a cost estimate, takes bids, then awards the contract, usually to the lowest responsible bidder.

How each member voted

OfficialVote
Kala AndersonAbsent
Chris CroneYes
Rob GroveYes
Lori LyonYes
Anna Bergman PierceYes

More from the record

Recorded in the minutes as: “5) Resolution: Consideration of approval of a resolution awarding contract [2026 Downtown Street Improvements Project], deferred during the April 6, 2026, regular city council meeting – Motion: to approve the resolution; seconded by Council Member Grove. Public Works Director/City Engineer Koester stated that additional information and documents were requested from apparent low bidder Brothers Concrete, as the City has not worked with them before as a prime contractor. After review of the requested documents, City staff recommends awarding contract to Brothers Concrete of Des Moines, IA, in the amount of $1,466,984.39. Council Member Pierce noted that there was not a significant spread between the lowest and second lowest bid, so she was comfortable moving forward as recommended by staff. Results of vote:”.

Motion as recorded: “to approve the resolution; seconded by Council Member Grove. Public Works Director/City Engineer Koester stated that additional information and documents were requested from apparent low bidder Brothers Concrete, as the City has not worked with them before as a prime contractor. After review of the requested documents, City staff recommends awarding contract to Brothers Concrete of Des Moines, IA, in the amount of $1,466,984.39. Council Member Pierce noted that there was not a significant spread between the lowest and second lowest bid, so she was comfortable moving forward as recommended by staff. Results of vote:”.

From the vote line in the official minutes, which names each member’s vote. Members not named in the vote line are shown as Not in the record unless the minutes list them absent. Vote line as printed: “Ayes: Crone, Grove, Lyon, Pierce. Nays: None. Absent: Anderson. Motion carried 4 – 0 – 1.”.

Source Full minutes for the whole Apr 20, 2026 meeting, p. 2 (saved copy) · All votes at this meeting

What you can do

Have your say

Agendas and minutes: city meeting portal

Contact the Waukee City Council

Write a letter

Contacts: city council page.

Get email alerts

A short email when the places you follow post new decisions, with links to the official record.

Sign up